Project Details:

This project was prioritized by the City Council Sidewalk Committee and will install a new sidewalk on the west side of Dunn Street from 15th to 16th Street.

Project Timeline:

  • Design: 2021
  • ROW Acquisition: 2021-2022
  • Construction: 2022

Bidding Documents:

Letting Date: June 17th, 2022, 11:30 AM  

Award Date: June 21st 2022

Zoom meeting link for Bid Opening-  Link

Bid (Open):

No pre-Bid meeting was scheduled for this project.

Results:

  • Milestone Contactors LP            $244,600.00
  • Groomer Construction                $203,365.36  (Awarded)

Project Contacts:

Patrick Dierkes

812.349.3913 or patrick.dierkes@bloomington.in.gov

 

Sara Gomez, Project Manager

812.349.3913 or gomezs@bloomington.in.gov